AquaShield staged test plan

Gate Test article Pass evidence Stop condition
AQ-0 Equations and calculator Independent unit review and reproduced outputs Unit or conservation error
AQ-1 Bench loop, no chamber Stable flow, gas separation, filtration, heat balance Cavitation, uncontrolled gas, leak
AQ-2 0.50 m³ uncrewed flexible cell Force mapping, drain, isolation, mass closure Entrapment geometry or failed isolation
AQ-3 Fault-injection rig Single-fault containment and manual egress fixture Inventory loss or software-dependent escape
AQ-4 Radiation transport model Mission-specific dose comparison with uncertainty No useful benefit at credible mass
AQ-5 Reduced-gravity uncrewed article Controlled liquid/gas interface and drainage Persistent gas pocket or loss of control
AQ-6 Human-factors ground protocol Independent medical/IRB approval first Approval absent or unacceptable hazard
AQ-7 Flight technology demo Agency safety approval and telemetry Any unresolved catastrophic hazard

AQ-2 falsification matrix

The concept fails its initial buildability gate if any of the following survives redesign:

Null results and stopped tests are reportable outcomes.